Tallaght Deep Retrofit & Redesign
| EXTENSION: | None |
| LAYOUT CHANGES: | Remove chimney breast and stack from centre of house Revised ground floor layout to add bathroom & utility. Relocate kitchen Minor layout changes at first floor |
| RETROFIT WORKS: | Insulate ground floor, Insulate external walls (dryline), Roof insulation, Acoustic insulation, Triple glazed PVC windows and doors, Airtightness, Ventilation system, Gas boiler, Zoned heating, Heating controls, Radiators, Plumbing, Re-wire, Low energy lighting. |
| FITTINGS & FINISHES: | Layout changes, Kitchen, Utility, Appliances, Bathroom, Shower room, Wardrobes, Storage, Electric Fire, Internal doors, Skirtings and architraves, Timber floors, Tiled floors, Carpet, Painting. |
| STAGES 1-5: | 13 months |
| STAGE 6: (CONSTRUCTION) | 24 weeks |

Project details
This house was our clients family. They were born and raised in this house.
The house was a lovely family home full of memories for our client and their extended family. However, it was dated and cold. It had been extended on two occasions and the layout was a little higildy-pigildy. There was a fire breast in the centre of the house which restricted room layout. Our client decided that it was time to reimagine the house and modernise it.
We redesigned the layout to provide a large open plan living area, linked discretely to the sitting room. The kitchen was relocated to the brightest part of the house and utility space and a full size shower room were added downstairs. Removal of the chimney breast improved the rooms upstairs.
A full suite of insulation retrofit works were carried out. The client opted for the familiarity of a gas boiler instead of a heat pump, and the finished house is BER B2 rated.